What's Change Control?

What's Change Control?

Change management is the process via which all requests to change the approved baseline of a project, programme or portfolio are captured, evaluated after which approved, rejected or deferred.

Change management is of particular significance when the project is part of a larger programme or portfolio because the consequential effects of unmanaged change could also be far-reaching within the planned change surroundings and to business-as-traditional activities.

The project professional implements the next steps to manage change:

Log change request in a change register (or log).
Initial evaluation the place the change is reviewed.
Detailed evaluation the place the impact on baseline success criteria, benefits, scope, quality, time, resources, costs, risks, stakeholder engagement or another criteria necessary to achieving the enterprise case are considered.
A advice is made to the sponsor and/or wider governance board to approve, reject or defer the change.
The plan is up to date is a change is approved.
Implementation where the mandatory actions are taken and monitored.
It is important to differentiate change control from the wider discipline of change management. Change management is a subset of general change administration and it is useful to not combine up the language. Change administration is a structured approach to move an organisation from a current state to a future desired state.

Change requests may arise on account of issues that occur from the administration of work or exterior sources. Points that end in changes to scope or another part of the baseline plan are progressed through change control.

Any success criteria that must be changed at any time within the project life cycle are subject to approval by means of change control. Formal change control is required when tolerances are breached

Change control is of particular importance when the project is part of a bigger programme or portfolio because the consequential effects of unmanaged change may be far-reaching within the deliberate change surroundings and to enterprise-as-traditional activities.

Change control contains five levels:

Proposing a Change
Abstract of Impact
Decision
Implementing a Change
Closing a Change
There are two documents used throughout the process:

Change Log: used to provide a report of all changes requested and selections made
Change Request Kind: used to doc details of the change, together with the enterprise case
1. Proposing a Change
This process gives the ability for anyone within the project staff (including the customer) to recommend a change to the project. The proposal must embrace a description of the change and anticipated benefits or different reason for the change. The change is introduced using the Change Request Form and added to the Change Log for the project.

2. Abstract of Impact
This process is carried out by the project manager, who will consider the overall effect on the project, covering the next items:

Quantifiable cost financial savings and benefits
Legal, regulatory or other unquantifiable reason for change
Estimated cost of the change
Impact on timescales
Extra resources needed
Impact on different projects and enterprise activities
New risks and points
After this evaluation, the project manager recommends whether to carry out the change.

3. Choice
This process involves a assessment of the change request by an approved creatority who will consider all the knowledge provided by the project manager and individual making the request. The decision will usually be:

Settle for
Accept with comments and particular conditions
Reject
Defer (change just isn't approved, but is left for consideration later)
4. Implementing a Change
If the change is approved it is deliberate, scheduled and executed at a time agreed with the stakeholders.

As part of the planning, a regression test plan is required in case the change must be backed out.

After implementation, it is usual to carry out a put up-implementation review.

5. Closing a Change
Once carried out, the requester checks and agrees on the change, and it is closed in the Change Log by the project manager.